| Item | Capacity | Comments |
|---|---|---|
| Diesel Generator | 200 kVA (160 kW) | 24hr runtime backup fuel |
| D M Water plant | 6 kl / hr | Additional storage in place |
| Boiler | 400 kg / hr | Pressure safety valve set kg / cm2g : 10.54 |
| Cooling tower | 125 TR | Connected to all SS mixing vessels |
| Air compressor | 70 CFM | Maximum working pressure 7 kg / cm2 |
| Scrubber | 3,000 CFM | PP/FRP Column with Inbuilt recirculation Tank |
| HVAC | 6k, 5k, 5k, 3.2k CFM | Mfg areas 1&2, Chemical & Micro lab, Filling area |
| Goods lift | 2,500 kg x 2 | RM store, PM Store |
| MHE | 2 Bo Stackers, HoPT | 1.5 Ton each, 2 Ton each (respectively) |
| Fire hydrant system | 2 hr inhouse water storage | GIDC Fire station at 500m from the unit |
| ETP | 30 kL / day | GIDC cETP connection and membership in place |
| Distribution transformer | 400 kVA | Installed |